BHM airport unveils first renovated restrooms in terminal
Reading time: 3 minutes

On Thursday, October 15, the Birmingham-Shuttlesworth International Airport (BHM) officially opened its first set of renovated terminal restrooms, kicking off a nearly $5 million project to give travelers a more comfortable place to go before they go.
Birmingham-Shuttlesworth International Airport gets a restroom upgrade

Following the ribbon-cutting ceremony, BHM airport leadership showed off the first set of renovated restrooms in the terminal, delivering modern, convenient and more accessible facilities for customers traveling through the airport.
Here’s what’s new:
- More privacy: New stall doors open outward instead of inward.
- No more guessing: Privacy locks indicate which stalls are occupied and which are available.
- Convenient handwashing: Updated stations are thoughtfully positioned near trash cans and paper towels.
- Family-friendly features: The family restroom includes a new adult changing station and nursing rooms for traveling parents.
- Modern fixtures: The spaces have been completely redesigned with updated fixtures and improved traffic flow.

According to Jennifer Egbe, Chair of the Birmingham Airport Authority (BAA), this is just the beginning.
“Before it’s all said and done, we will spend nearly $5 million on complete makeovers on the concourse restrooms. We want the customer experience to be top notch every time you fly through BHM, and we’re taking strides every day to reach that goal.”
Jennifer Egbe, Board Chair, Birmingham Airport Authority
The Federal Aviation Administration (FAA) is covering 95% of the project through its Airport Terminal Project (ATP) grant program, funded through the Bi-partisan Infrastructure Law that provides competitive grants for terminal development projects that address aging infrastructure and provide safe, sustainable, and accessible facilities.

So what’s next? Contractor Construction Works, Inc. will begin work on the second set of restrooms immediately with the closing of facilities near the B1 gate.
“We have phased the project in such a way that only one set of restrooms will be closed at any given time. We are working to minimize the inconveniences while delivering first class facilities for travelers.”
Marcelo Lima, Vice President of Planning and Development at BHM
According to the BAA, the project is expected to be completed in October of 2027.